Konya Şeker – Biogas Balloon Installation

Project Description

Customer: Konya Şeker San. ve Ticaret Co. Inc.
Location: Konya
Working: Installation Process
Capacity: 2000m³
Gas Permeation Capacity: 1000m³/h
Material: PVC Coated on Woven Polyester
Start Date: 28.12.2023
End Date: 11.02.2024

Work Done: Konya Şeker San. Ve Tic. Seydibey TÜİET biogas balloon inner membrane supply and installation.

Explanation

Biogas balloon disassembly, internal balloon repairs, external membrane supply and assembly and commissioning with all equipment.

Eti Maden – Demineralized Water Plant

Project Description

Customer: Eti Maden Kırka Kırka Borax Business Directorate
Location: Eskişehir
Start Date: 20.06.2023
End Date: 20.07.2023

Work Done: Energy Unit Demineralized Water Plant Cation anion and mix-bed nozzle replacement work.

Description

Approximately 2500 single and double-sided existing filter nozzles were disassembled and new nozzles were installed in their places.

Eti Maden – Demineralized Water Plant

Project Description

Customer: Eti Maden Kırka Kırka Boraks Business Directorate
Location: Eskişehir
Capacity: 20m3/h
Fans: 2 Units. Each fan capacity 2500Nm3/h, material stainless.
Pumps: Horizontal Centrifugal monoblock, 20m3/h, 3 bar, material stainless.
Start Date: 28.02.2023
End Date: 29.05.2023

Works Done: Energy Unit Demineralized Water Plant Degasser system design, construction and delivery.

Explanation

The existing deaerator was disassembled and taken to the scrap yard. The new deaerator system (including air fans and pumps) was assembled, tested and delivered.



Eti Maden – Bandırma

Project Description

Customer: Eti Maden Bandırma Boron and Acid Factories Operation Directorate
Location: Bandırma
Start Date: 23.03.2022
End Date: 22.08.2022

Works Done: Energy Unit Demineralized Water Plant Chemical dosing unit construction. Demineralized Water plant Chemical dosing unit design, manufacturing, assembly and delivery.

Explanation

1 dosing unit was built for approximately 150 m3/h demineralized water plant.

Dosing Unit Appearance

Dosing Unit Static Mixer for Sulfuric Acid Solution View

Eti Maden – Acid Measurement Tank

Project Description

Customer: Eti Maden Kırka Kırka Borax Operations Directorate
Capacity: 5m3
Material: ST 37, Solution contact surfaces are coated with neoprene.
Start Date: 09/15/2021
End Date: 12/10/2022

Works Done: Energy Unit Demineralized Water Plant Acid measurement tank supply and installation

Explanation

The existing acid measuring tank was disassembled and taken to the scrap yard. The new acid measuring tank was assembled, tested and delivered.

HCl Solution Preparation Tank Appearance During Installation

HCl Solution Preparation Tank Label

Appearance After Installation of HCl Solution Preparation Tank

Konya Şeker – Biogas Balloon Installation

Project Description

Customer: Konya Şeker San. ve Ticaret Inc. Co.
Location: Konya
Work: Installation Process
Capacity: 2000m³
Gas Passage Capacity: 1000m³/h
Start Date: 02/17/2021
End Date: 03/19/2021

Explanation

Biogas balloon disassembly, internal balloon repairs, external membrane supply and assembly and commissioning with all equipment.

Konya Şeker – Biological Desulfurization Unit

Project Description

Customer: Konya Şeker San. ve Ticaret Inc. Co.
Location: Konya
Work: Installation Process
Start Date: 14.07.2019
End Date: 25.09.2019

Work Done: Konyaşeker San. ve Tic. A.Ş. Purchase of Seydibey TÜİET Biological Desulfurization Facility and disassembly, transportation and installation of an existing Biological Desulfurization unit to its new location.

Explanation

Purchase of Biological Desulphurization System:According to biogas analysis, biological desulphurization capacities were determined, after the projects and manufacturing were completed, the assembly was carried out on site. The biological desulphurization facility was delivered to our customer after the testing and commissioning processes.

Relocation of Existing Biological Desulphurization System and Installation in New Location: The biological desulfurization unit serving in the Konya Şeker Çumra Sugar Factory Biogas Conditioning Unit was disassembled and transported to its new location in Seydibey facilities and assembled. The facility was tested, commissioned and delivered to the customer.

Konya Şeker – Biogas Balloon

Project Description

Customer: Konya Şeker San. ve Ticaret Inc. Co.
Location: Konya
Work: Installation Process
Start Date: 08.05.2019
End Date: 24.05.2019

Information

Work Done: Konya Şeker San. Ve Tic. A.Ş. Transportation of the biogas balloon within the scope of electricity production and sales from Seydibey TÜİET Solid Waste Facility and installation in its new location.

Explanation: Biogas balloon foundation project, project of the platform on which the balloon will sit, dismantling of the existing biogas balloon, assembly in its new location.